Tunnel-14 Breakthrough 2026: 6.59 km Rishikesh-Karnaprayag Rail Tunnel Completed in Rudraprayag

On 27 Nov 2026 Indian Railways achieved the main breakthrough of the 6.59 km Tunnel-14 (dug from the Sumerpur and Marora portals) on the 125 km Rishikesh-Karnaprayag new rail line in Rudraprayag district, Uttarakhand.

Key facts

Event

Main breakthrough of Tunnel-14, 27 Nov 2026

Tunnel length

6.59 km

Location

Rudraprayag district, Uttarakhand

Key facts

Excavated from

4.7 km from Portal-1 (Sumerpur) and 1.79 km from Portal-2 (Marora)

Project

Rishikesh-Karnaprayag new rail line, 125 km

Tunnels in project

16 main-line tunnels + 12 escape tunnels

Timeline

11 May 2017

Railways entrusts RVNL with the Final Location Survey for Char Dham rail links; PIB notes the Rishikesh-Karnaprayag line is under construction by RVNL

Mar 2024

Main tunnel drive of Tunnel-14 launched at Portal-2 (Marora) after slope stabilisation

30 Jul 2025

Railway Minister tells Lok Sabha that 199 km of 213 km tunnelling is done and the TBM-driven T-8 has broken through

11 Feb 2026

Lok Sabha reply: 99 km of main-line tunnels and 9 escape tunnels completed; 8 of 19 major bridges done

29 Jul 2026

Lok Sabha reply: 101 km of the 104 km main-line tunnels and over 95 km of escape tunnels done; 11 of 19 major bridges complete

For your exam

UPSC

GS III: infrastructure (railways), tunnelling in fragile Himalayan geology; GS I: geography of Uttarakhand; Prelims: project length, districts, T-8 TBM

SSC

Static plus current GK: Tunnel-14 is 6.59 km long, in Rudraprayag district; project is 125 km long and lies wholly in Uttarakhand

Banking

One-liner on railway infrastructure: date, tunnel length, district and state

Railways

RRB NTPC/Group D: Rishikesh-Karnaprayag line, 16 main-line tunnels, longest tunnel T-8 (14.8 km), first TBM use in Himalayan geology by Indian Railways

Daily current affairs on RankVyuh

Tunnel-14 Breakthrough 2026: 6.59 km Rishikesh-Karnaprayag Rail Tunnel Completed in Rudraprayag

Tunnel-14 breakthrough: on 27 Nov 2026 Indian Railways broke through the 6.59 km tunnel on the Rishikesh-Karnaprayag line in Rudraprayag, Uttarakhand.

Read the full article