Current affairs
On 27 Nov 2026 Indian Railways achieved the main breakthrough of the 6.59 km Tunnel-14 (dug from the Sumerpur and Marora portals) on the 125 km Rishikesh-Karnaprayag new rail line in Rudraprayag district, Uttarakhand.
Key facts
Event
Main breakthrough of Tunnel-14, 27 Nov 2026
Tunnel length
6.59 km
Location
Rudraprayag district, Uttarakhand
Key facts
Excavated from
4.7 km from Portal-1 (Sumerpur) and 1.79 km from Portal-2 (Marora)
Project
Rishikesh-Karnaprayag new rail line, 125 km
Tunnels in project
16 main-line tunnels + 12 escape tunnels
Timeline
11 May 2017
Railways entrusts RVNL with the Final Location Survey for Char Dham rail links; PIB notes the Rishikesh-Karnaprayag line is under construction by RVNL
Mar 2024
Main tunnel drive of Tunnel-14 launched at Portal-2 (Marora) after slope stabilisation
30 Jul 2025
Railway Minister tells Lok Sabha that 199 km of 213 km tunnelling is done and the TBM-driven T-8 has broken through
11 Feb 2026
Lok Sabha reply: 99 km of main-line tunnels and 9 escape tunnels completed; 8 of 19 major bridges done
29 Jul 2026
Lok Sabha reply: 101 km of the 104 km main-line tunnels and over 95 km of escape tunnels done; 11 of 19 major bridges complete
For your exam
UPSC
GS III: infrastructure (railways), tunnelling in fragile Himalayan geology; GS I: geography of Uttarakhand; Prelims: project length, districts, T-8 TBM
SSC
Static plus current GK: Tunnel-14 is 6.59 km long, in Rudraprayag district; project is 125 km long and lies wholly in Uttarakhand
Banking
One-liner on railway infrastructure: date, tunnel length, district and state
Railways
RRB NTPC/Group D: Rishikesh-Karnaprayag line, 16 main-line tunnels, longest tunnel T-8 (14.8 km), first TBM use in Himalayan geology by Indian Railways
Daily current affairs on RankVyuh
Tunnel-14 breakthrough: on 27 Nov 2026 Indian Railways broke through the 6.59 km tunnel on the Rishikesh-Karnaprayag line in Rudraprayag, Uttarakhand.