A can finish a job in 12 days and B in 18 days. Working together, in how many days will they finish it?
SSC CGL · Time and Work
- A. 7.2 daysCorrect
- B. 7.5 days
- C. 8 days
- D. 6 days
Answer: A. 7.2 days
A does 1/12 and B does 1/18 of the work a day. Together: 1/12 + 1/18 = 3/36 + 2/36 = 5/36 a day. The whole job takes 36/5 = 7.2 days.